Dependencies are promises. Most of them were never made.

Why do dependencies between teams keep failing, and what makes one reliable?

Most plans are reliable about their own work and optimistic about everyone else's. The plan says the data platform will be ready in March because the data team's plan says March, and nobody asked the data team whether March was a promise or a hope. When March becomes June, the waiting work finds out last, and the question asked is why the data team let everyone down. Often the better question is whether the data team ever agreed to anything.

Where execution breaks

Sull, Homkes and Sull's research on strategy execution found that it fails between units more than within them: managers say they can rely on their own boss and direct reports far more than on colleagues in other functions and units [1]. The larger of their samples, about 11,000 managers reported by London Business School in 2015, put a number on the far side of that boundary. Only about one in ten said they could always rely on colleagues in other units to deliver [2].

That is self-report, and it measures confidence rather than delivery. But confidence is what a plan's dates are made of. A strategy of any size depends on work crossing boundaries: the new service needs the platform, the platform needs the security review, the rollout needs the training team. If the people who wrote the plan do not believe the handovers in it, the dates downstream of those handovers are not really dates.

Why would teams be so much more reliable inside than across? It is not that other teams are less competent. My reading is simpler. Inside a team, commitments are made out loud: a manager asks, someone agrees, and the work is checked when it lands. Across teams, the commitment is often never made at all. One plan assumes it; the other plan never heard about it.

A dependency is a promise

Sull and Spinosa made the case in 2007 that execution runs on promises between a customer and a provider, made in three phases: a meeting of minds, making it happen, and closing the loop, where the customer declares whether the work was delivered. Good promises, in their account, are public, active, voluntary, explicit and mission based [3].

Figure 1. Sull and Spinosa's three phases of a promise
  1. A meeting of minds

    The customer and the provider settle what each means, and who else needs to be involved.

  2. Making it happen

    The provider does the work.

  3. Closing the loop

    The customer declares whether the work was delivered.

Sull and Spinosa, Harvard Business Review, 2007 [3]

It is a framework, not a measurement, but it makes a useful test. Read a typical dependency against those five qualities.

Figure 2. A typical dependency, tested against the five qualities of a good promise
QualityTypical dependencyAgreed request
PublicA typical one lives in the waiting team's plan, where the provider cannot see itNoYes
ActiveNobody asked; someone wrote it downNoYes
VoluntaryAssumed from a date that was never meant as a commitmentNoYes
ExplicitA word like "data", which both sides can read differentlyNoYes
Mission basedRarely says what aim it serves, so nobody can tell what should giveNoPartly

The five qualities are Sull and Spinosa's [3]. How a typical dependency fares is my assessment.

By that test, most dependencies fail before anyone breaks a promise, because no promise was made. That changes what to fix. More reporting on dependencies will not help if the dependencies themselves are assumptions. The first step is to turn each one into a request that someone can accept.

Two promises that look like one

There is a second, quieter problem. "We need the platform" can mean two different things. It can mean the waiting work cannot start until the platform is ready. Or it can mean the waiting work can start in parallel, but cannot finish without it. Project schedulers will recognise these as finish-to-start and finish-to-finish.

The difference matters to the provider. A team that knows its work is only needed before the other team finishes may have months more room than one that thinks it is blocking a start. Without being told which, the provider either over-commits or quietly assumes the easier one. Asking the question is part of making the promise explicit.

Figure 3. Two kinds of need, and a conflict Illustrative example, not data

A data platform is due to finish at the end of June. A new service needs it before it starts in July, which fits. A reporting project starts in March but only needs it before it finishes in September, which also fits. A customer portal needs it before it starts in April, which is a conflict of three months.

  • The platform being waited for
  • Work that is waiting
  • When the platform is needed

Data platform

New service, needs it before it starts Fits

Reporting, needs it before it finishes Fits

Customer portal, needs it before it starts Conflict of 3 months

Show the figures as a table
WorkStartsFinishesNeeded by
Data platformJanJun–
New service, needs it before it startsJulSepStart of Jul
Reporting, needs it before it finishesMarSepEnd of Sep
Customer portal, needs it before it startsAprAugStart of Apr

When the dates do not fit

Sooner or later a promised handover will be planned to land after it is needed. The tempting response is to move a date. The waiting work's start slips, or the provider's finish is pulled forward on paper, and the plan looks consistent again.

Both hide the problem. A plan that adjusts dates to fit is a plan that never tells anyone something went wrong. The better response is to show the timing gap as a gap, with both owners named and the size of the overlap visible, and let them decide what to do: re-plan, re-scope, find the work somewhere else, or accept the risk knowingly.

What to do

Write each dependency as a request from one owner to another. Say what is needed, described so that the other owner could check it was delivered: "the new case data feed, tested and live" rather than "data". Say whether it is needed before the waiting work starts or before it finishes.

Have the request accepted or declined by the owner who will keep it, and ask for a reason if it is declined. Until it is accepted, show it as proposed, not as part of the plan.

Keep declined requests visible. A declined request is not a failure of the process. It is the process working: the organisation has found out, early, that something it assumed is not going to happen.

Compare the dates and show the conflicts, including handovers with no spare time at all. Do not move dates automatically.

When the work is delivered, the waiting owner says so. That is the loop closed.

I should be clear that this is my reading of the research applied to planning, not something the research tested. What the research does show is where execution breaks, and it is exactly here, between teams, where commitments are least explicit. For the same idea applied inside an IT department, see the step on dependencies in how a CIO connects IT strategy to business outcomes. For the check that comes before it, whether the work is aimed at anything at all, see how to tell whether your portfolio supports your strategy.

One line on waytrk

In waytrk a dependency is proposed by one Initiative's Owner and becomes confirmed only when both Owners confirm it; rejecting one, or declining a request for new work, needs a reason. Each dependency says what is handed over and whether it is needed before the waiting work starts or finishes, and waytrk shows timing conflicts but never moves a date.

References

Every figure above points at an entry in the evidence base, which records the source, its method, its grade and its limits.

  1. Sull, D., Homkes, R. and Sull, C. (2015) Why strategy execution unravels, and what to do about it. Harvard Business Review, March 2015. Original source (opens in a new tab)

    Grade BGrade BA named survey or study that states its method and sample. Register entry 3

  2. London Business School (2015) release on Sull, D., Homkes, R. and Sull, C., Why strategy execution unravels; the HBR article of March 2015 reports an earlier, smaller sample. Original source (opens in a new tab)

    Grade BGrade BA named survey or study that states its method and sample. Register entry 2

  3. Sull, D. and Spinosa, C. (2007) Promise-based management, the essence of execution. Harvard Business Review, April 2007. Original source (opens in a new tab)

    Grade CGrade CAn argued source, such as a book or a method, rather than a measurement. Register entry 4

Project dependency mapping: who promised what?

What am I looking at?

An article from our knowledge centre on turning strategy into delivery. Every figure is traced to its source, with its limits.

Words on this page

Initiative
A piece of planned work.
Function
A team, department or service, with its own plan.
Dependency
One piece of work needs another to finish first.
Timing conflict
Work planned to start, or finish, before the work it needs has finished.
Owner
Keeps a Function's plan current and decides on suggested changes.