Put two lists side by side: the aims your organisation has agreed, and the work it is paying for. Then mark every initiative with the aim it serves, and every aim with the initiatives that move it. The gaps you find on either side are the answer. Work with no aim, aims with no work, and links that nobody could defend are three different findings, and each has a different fix. It takes an afternoon the first time and an hour a quarter after that.
Four aims on the left and five pieces of work on the right, joined where an owner can say which aim the work serves. Improve staff retention has nothing aimed at it, the office refurbishment serves no aim, and the website rebuild is linked to online self-service on paper only.
Aims the board agreed
Work being paid for
- Resolve complaints faster
- Cut repeat visits
- Improve staff retention Nothing aimed at it
- Grow online self-service
- Case management system
- Scheduling upgrade
- Data cleansing
- Office refurbishment No aim
- Website rebuild
- Linked, with a reason the owner can give
- Linked on paper, but the owner cannot say what it changes
That is the whole method. The rest of this guide is how to do it so the answer is honest.
Check the aims can be aimed at
If nobody can say what would change, note it.
Build the two lists
Aims as agreed; work from what is funded.
Link in the owner's words
One aim and one sentence of reason for each initiative.
Read the gaps
Three kinds of finding, each with its own fix.
Look one level down
Which functions must get better, and is anything making them better?
Before you start: can the strategy be supported at all?
The check assumes your aims are things work can be aimed at. Many are not. Richard Rumelt's description of bad strategy is a list of goals or a statement of ambition with no diagnosis of the problem and no coherent action [1]. "Be the partner of choice" is not something an initiative can serve; it is something every initiative can claim to serve, which is the same as none.
So read the aims first. For each, ask: what would have to be different for this to be achieved, and which part of the organisation would make that difference? If nobody can say, note it. That aim will show up with lots of work against it or none, and neither tells you anything until it is rewritten as an outcome someone can move.
Step one: build the two lists from what exists
Take the aims from the strategy as agreed, at the level the board would recognise. Take the work from wherever money and people are actually committed: the portfolio register, the change budget, each function's plan. Use what is funded, not what is proposed.
Expect the second list to be longer and messier than you would like. That is part of the finding.
Step two: link each initiative to an aim, in the owner's words
For each initiative, ask its owner which aim it serves and why. Write down the aim and one sentence of reason. Do not accept "all of them" or "the strategy". An initiative that serves everything is usually one whose business case was written after the strategy, by copying its headings.
This is where the evidence about line of sight bites. Sull, Homkes and Sull's research, reported by London Business School from about 11,000 managers, found that only about a third of senior managers could name their firm's top three priorities [2]. If the people approving work cannot name the aims, the links on paper were made by whoever wrote the business case, and nobody checked them. Asking the owner directly is the check.
Step three: read the gaps
You will have three kinds of finding.
Work with no aim
Label maintenance as maintenance, write unrecorded priorities into the strategy, and stop work that has outlived its reason.
Aims with no work
The most important finding, and invisible in any report built from the project list. Decide now, not at the year-end review.
Links that would not survive a question
For each link, ask what would move and how you would know.
Work with no aim. Some of it is maintenance: keeping the lights on, meeting a regulation, replacing what is failing. That is legitimate, but it should be labelled as such, so it stops competing for strategic attention and money. Some is a decision nobody wrote down, a priority the executive holds but never put in the strategy. That should go into the strategy or be stopped. And some is work that has outlived its reason. Treat "no link" as a finding to explain, not a failure to hide.
Aims with no work. These are the aims the organisation has agreed to but not started. They are the most important finding, because they are invisible in every report built from the project list: a project report can only show projects. If an aim matters and nothing moves it, that is a decision to make now, not at the year-end review.
Links that would not survive a question. An initiative tagged to an aim, where the owner cannot say what it changes for that aim. Kaplan and Norton built strategy maps to make these cause-and-effect chains explicit, linking objectives so that each one shows what it depends on [3]. You do not need the full method to borrow the test: for each link, can you say what would move, and how you would know?
Step four: look one level down, at the functions
Initiatives are where change is funded. Functions are where it lands. A strategy that needs a function to do something it cannot yet do is resting on a capability gap, and an initiative list will not show it.
Capability-based planning, as the TOGAF guidance on business capability planning sets it out, describes the organisation by what it can do, independent of its current structure, and plans change against the capabilities that have gaps [4]. For the check, the lighter version is enough: for each aim, name the functions that must get better at something, and see whether any initiative or any function's own plan is making them better. Where neither is, you have found an aim with no work that the initiative list would have hidden.
Why this is worth an afternoon
The cost of not doing it is measurable, if roughly. PMI's 2018 survey of project practitioners, senior executives and PMO directors found that organisations which undervalue project management as a strategic competency reported an average of 50% more of their projects failing outright, and that 9.9% of every dollar invested was wasted through poor project performance [5]. That is a professional body's survey of its own field, and I would not put much weight on the precise figures. But it points the same way as the rest of the evidence: the money is lost in the connection between what was decided and what was done, and most organisations do not look there.
What I recommend, as a method rather than a finding: run the check once properly, then keep the two lists joined. Every new initiative names its aim before it is approved. Every aim shows its work at every review. "No link" and "no work" are reported as findings, alongside the status colours, not instead of them.
If you want the reasoning behind why the gap sits here, I wrote about how much of a strategy typically gets delivered and where the rest goes, and about what the research says planning is good for.