More than most change plans assume, and there is no reliable general figure you can borrow. The nearest published evidence is about technology budgets: in Deloitte's 2018 global CIO survey, respondents put about 55% of IT budgets on running business operations, and the authors note that only a few years earlier more than 70% was not unusual [1]. That is the function most associated with change, so other functions are unlikely to have more room. The honest answer for your own teams is to measure it, and it takes an afternoon per function.
- Time left after must-do work
- Time the new system needs
Show the figures as a table
| Series | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Time left after must-do work | 70% | 70% | 40% | 20% | 15% | 20% | 40% | 50% | 60% | 55% | 60% | 70% |
| Time the new system needs | – | – | – | 40% | 40% | 40% | 40% | – | – | – | – | – |
Invented figures for one team, to show the form. The time left is what remains after year-end, the statutory accounts, the audit and a contract renewal.
Why the plan gets it wrong
A change plan is built from the change work, so it counts as free the time that must-do work has already claimed. The bias is familiar from research on individual estimates. Buehler, Griffin and Ross found that people predicting how long their own tasks will take focus on the plan ahead rather than on relevant past experience, and their predictions are too optimistic; in one study the bias disappeared when people were asked to connect past experience with the prediction [2]. Those were students estimating their own work, so I apply it to organisations by analogy. But must-do work is exactly the past experience a plan ignores: the same returns, audits and renewals fall in the same months every year.
How to measure it
Take one function and last year's calendar, not this year's plan.
- List the must-do work: everything the law, a contract, safety or keeping the service running required. Statutory returns, audits, renewals, inspections, licence and equipment replacements.
- Put each on the calendar where it actually fell, with the people it took.
- Estimate the effort from what happened, not from what was planned. Ask the people who did it.
- Work out the share of the function's effort it took, month by month as well as over the year.
The monthly view matters more than the annual one. A function that spends 40% of its year on must-do work may spend 90% of March on it, and March is when your change plan wanted their time.
Then plan change into what remains, around the fixed dates rather than over them. The wider argument, including how to stop "business as usual" becoming a place to hide work, is in plan change around the work that has to happen anyway. How to see change piling onto the same people is in what change saturation is.
waytrk shows must-do work on the same plan as change, with its reason and dates, so the months where they collide are visible before the change is approved.