Change saturation is what happens when more change lands on the same people, at the same time, than they can absorb. Each change may be well planned and reasonable on its own. The trouble is the total, and nobody is usually responsible for the total. You measure it by recording how much each change affects each group of people, month by month, and putting the results on one picture: groups down the side, months along the top. The months where several large changes meet on one group are where saturation will show.
| Group | Jan | Feb | Mar | Apr | May | Jun |
|---|---|---|---|---|---|---|
| Contact centre advisers | Jan: 1 Small | Feb: 3 Substantial | Mar: 5 Fundamental | Apr: 4 Major | May: 2 Some | Jun: 1 Small |
| Team leaders | Jan: 1 Small | Feb: 2 Some | Mar: 3 Substantial | Apr: 3 Substantial | May: 1 Small | Jun: 0 None |
| Field engineers | Jan: 0 None | Feb: 0 None | Mar: 1 Small | Apr: 2 Some | May: not assessed | Jun: not assessed |
- 0 None
- 1 Small
- 2 Some
- 3 Substantial
- 4 Major
- 5 Fundamental
- Not assessed
Each cell shows the largest single impact landing on that group that month. Impacts are not added together, so look at how many changes sit behind a cell as well as its colour. The groups and ratings are invented to show the form.
The colour is a warning, not a measured limit. A dark cell shows one large change; three moderate changes in the same month show as one moderate colour, which is why the number of changes behind a cell matters as much as its shade. No picture tells you how much a group can absorb: that stays a judgement for the people who know the group.
Why it matters now
People's willingness to absorb change is not a fixed resource. Gartner reported that the share of employees willing to support enterprise change fell from 74% in 2016 to 38% in 2022 [1]. Gartner does not publish the survey's sample alongside the figures, so treat them as a direction rather than a measurement of your organisation. But they suggest that the capacity a portfolio draws on has been getting scarcer.
There is also evidence that managing the people side of change is worth the effort. Prosci reports that, among more than 2,600 change practitioners rating their own projects, those with excellent change management met or exceeded their objectives 88% of the time, against 13% with poor change management [2]. Those are self-reported figures from a firm that sells change management, so I would not quote them as a forecast. Even heavily discounted, the gap is worth acting on.
How to measure it
For each change, name the groups of people it affects and rate how much their work changes, from none to fundamental. Rate each group separately: a new system can be a small change for managers and a fundamental one for the people who use it all day. Record when the change lands on them.
Then read the picture before approving the next change. If a group already has two major changes in March, the business case for a third should say what it will do about that: move, phase the change, or pay for extra support. Show anything nobody has assessed as unknown, not as high risk and not as no impact.
The longer argument, including why the total is so rarely added up, is in change impact: the people cost nobody adds up. How to rate readiness as well as impact is in what ADKAR is and how to use it across a portfolio.
waytrk records change impact for each affected group and draws exactly this heat map, with unassessed work shown as unknown.