Every business case counts its own cost. Very few count the cost it adds to people who are already absorbing three other changes. Each Initiative is approved on its own merits, and each, taken alone, is reasonable. The sum lands on the same teams in the same months, and nobody added it up, because adding it up was nobody's job.
The willingness to change is not unlimited
Gartner reported that the share of employees willing to support enterprise change fell from 74% in 2016 to 38% in 2022 [1]. Gartner does not publish the survey's sample or method alongside those figures, so I would read them as a direction of travel rather than a measurement of any particular organisation. But the direction matters. A strategy that needs people to work differently is drawing on something that appears to be getting scarcer, and most portfolios spend it without keeping any account of it.
- 2016
- 2022
Share of employees willing to support enterprise change 2016 74%, 2022 38%
Gartner Business Quarterly, 2023; the survey's sample is not published [1]
Why nobody adds it up
Change is approved one Initiative at a time. The business case for a new case management system describes its impact on the contact centre. The business case for a new rota pattern describes its impact on the contact centre. The restructure that merges two teams describes its impact on the contact centre. Each was reviewed by a different board, in a different month, against its own benefits, and each impact statement was accurate.
The contact centre experiences all three in the same quarter.
A project list cannot show this, because it is organised by project. What shows it is the same information turned round: the teams down the side, the months along the top, and in each cell how much change is landing there. Once it is drawn that way, the month where three large changes meet on one team is obvious. Before it is drawn, it is invisible to everyone except the team.
| Team | Jan | Feb | Mar | Apr | May | Jun |
|---|---|---|---|---|---|---|
| Contact centre | Jan: 1 Small | Feb: 2 Some | Mar: 5 Fundamental | Apr: 4 Major | May: 2 Some | Jun: 1 Small |
| Field service | Jan: 0 None | Feb: 1 Small | Mar: 1 Small | Apr: 2 Some | May: 2 Some | Jun: 1 Small |
| Finance | Jan: 0 None | Feb: 0 None | Mar: not assessed | Apr: not assessed | May: 1 Small | Jun: 0 None |
| People team | Jan: 1 Small | Feb: 1 Small | Mar: 2 Some | Apr: 3 Substantial | May: 1 Small | Jun: 0 None |
- 0 None
- 1 Small
- 2 Some
- 3 Substantial
- 4 Major
- 5 Fundamental
- Not assessed
Each cell shows the largest single impact landing on that team that month. Impacts are not added together, so look at how many changes sit behind a cell as well as its colour. The teams and ratings are invented to show the form.
Does managing it make a difference?
The most quoted evidence comes from Prosci's benchmarking research. Prosci reports that, in its most recent Best Practices in Change Management study, which asked more than 2,600 change practitioners about their work, projects with excellent change management met or exceeded their objectives 88% of the time, against 13% for projects with poor change management: about seven times as often [2].
Prosci, from more than 2,600 change practitioners rating their own projects [2]
The caveats are real. The practitioners rated their own change management and their own outcomes. Prosci does not give the number of respondents in each group, and it sells change management services. I would not quote "seven times" as a forecast for any project. I would quote it as evidence that the people closest to the work see a large gap between change that is managed and change that is not, and that even a heavily discounted version of that gap is worth acting on.
Impact and readiness are different questions
For each group of people an Initiative affects, there are two things worth recording.
How much changes for them. Not a single rating for the whole Initiative, but a rating for each group, across the parts of their work that might change: processes, systems, tools, roles, behaviours, reporting lines, where they work. A new system can be a small change for the managers who read its reports and a fundamental one for the people who use it all day. Rating them together averages away the group that matters most.
How ready they are. Here a model helps. Jeff Hiatt's ADKAR model, published by Prosci, describes the sequence an individual goes through in change: awareness, desire, knowledge, ability and reinforcement [3]. It is a model rather than a measurement, but it earns its place because each low score points to a different kind of help. Low knowledge means guidance and training. Low desire means a conversation with a manager about what worries people, not another all-staff email. A readiness rating that does not tell you what to do next is just another colour.
Awareness
Low? Explain why the change is happening.
Desire
Low? A conversation with a manager about what worries people.
Knowledge
Low? Practical guidance and training.
Ability
Low? Time and support to practise the new way of working.
Reinforcement
Low? Support that keeps the change working afterwards.
The five elements are from Jeff Hiatt's ADKAR model, published by Prosci [3]. The help each points to is my reading.
Unknown is not the same as high risk
The first time you map change impact across a portfolio, most of the map will be blank. It is tempting to treat blanks as red, on the grounds that unassessed change is risky. Resist it. A map that is mostly red is a map people stop looking at, and it hides the cells that really are red among the ones that are merely blank. Treating blanks as green is worse, because it hides the blanks themselves.
Show unassessed work as unknown. Count it, show where it sits, and work the count down. A visible "not assessed" is the system working.
What to do
For each Initiative, name the groups of people it changes, the team each belongs to, and when the change lands on them.
For each group, rate how much each part of their work changes, and rate their readiness where you can.
Put it all on one picture: teams down the side, months along the top, and each cell showing the largest single impact landing there and how many changes sit behind it.
Read the picture before approving the next Initiative. If a team already has two major changes landing in March, the third business case should say what it will do about that: move, phase the change, or pay for the extra support. If the decision is to go ahead anyway, write down what it was based on.
Keep "not assessed" visible, and count it.
This is the people side of the problem I described in dependencies are promises: work that crosses a boundary needs agreeing with the people on the other side, and change that lands on a team is work crossing a boundary too. It is also one of the places where the missing third of a strategy quietly goes.