A decision made in March looks different in September. If it went well, it looks obvious. If it went badly, it looks careless. Either way, the people in the room in September are judging it with something the people in March did not have: the outcome. That is how a strategy review turns into an argument about old decisions, and it is why the cheapest governance there is costs a few lines written at the time, saying what the decision was based on.
The decision, in March
Write down the basis, the owner, the risks accepted and what would reopen it.
A fact in the basis changes
Reopen the decision then, not at the next review.
The review, in September
Start from the record. What did we know, and has it changed?
What hindsight does to a decision
Wasserman, Lempert and Hastie summed up the research on hindsight in 1991: when people know how an event turned out, they usually cannot reproduce the judgements they would have made without that knowledge, and they do not realise that they cannot [1]. Their own experiment added a detail that matters for any review meeting. When the outcome was put down to chance, such as an unexpected storm, the hindsight effect almost disappeared. When it was put down to human skill, or the lack of it, the effect was sizable.
A review of a decision is, almost by definition, about skill and judgement. So the meeting where we most need a fair view of an old decision is the one where hindsight is likely to be strongest. Someone asks why the organisation committed to the new platform in March, and nobody can reconstruct what was known then: which options were on the table, what the cost estimate was, which risks were accepted knowingly. In that gap the decision is judged by its result, and the discussion goes round again.
A record does not cure hindsight. It gives the room something to check it against.
What a decision record needs
Four things, none of which takes long to write.
The decision and its owner
One sentence, and the name of the person who made it.
What it was based on
The facts, estimates and assumptions, and the options considered and why they lost.
What would reopen it
A date, or a change in one of the facts it rests on.
What was accepted as a risk
What could go wrong that was seen and accepted, rather than missed.
The basis is the part most often missing, and the most useful. A decision based on "the supplier delivers by June" and "demand stays at last year's level" can be reviewed in a minute when either changes. The question is no longer "was this a good decision?" but "does it still stand now that its basis has changed?" That question has an answer, and it is fair to the person who made the decision.
Estimates belong in the basis
Many decisions rest on an estimate of cost, time or benefit. HM Treasury's guidance on optimism bias states that project appraisers are systematically over-optimistic about all three, and that estimates should be adjusted using evidence from past projects [2]. Recording the estimate as part of the basis does two jobs. Later, it shows which number the decision relied on. At the time, it invites the question the Treasury asks: has this been adjusted for what usually happens? The Treasury's uplift percentages are UK public-sector figures, and I would not borrow them unchanged. The principle travels further than the numbers.
A decision needs a strategy to rest on
Some decisions cannot be given a basis, because the strategy they serve offers nothing to rest on. Richard Rumelt describes bad strategy as a list of goals or a statement of ambition with no diagnosis and no coherent action [3]. A decision justified as "supports our ambition to be the partner of choice" has no basis anyone could check. If the honest basis is "the strategy says so", and the strategy says nothing specific, that is worth knowing, and worth saying, before the decision rather than after it.
Look for the failure before it happens
For the big decisions there is one more step worth taking before the record is closed. Gary Klein's premortem asks a team to imagine that the plan has already failed and to explain why. It draws on a 1989 study by Mitchell, Russo and Pennington, and the study is worth reading accurately. People asked to explain an outcome presented as certain gave more reasons for it than people explaining the same outcome presented as uncertain: about 4.5 against 3.3 in the first of two experiments, and 4.6 against 3.3 in the second. Whether the event was set in the past or the future made no reliable difference [4].
- Outcome presented as certain
- Outcome presented as uncertain
Mitchell, Russo and Pennington, 1989, mean reasons given per outcome [4]
You will often see this quoted as "prospective hindsight improves the ability to identify reasons by 30%". The paper does not say that. It counted reasons and did not judge whether they were right, and the effect came from treating the outcome as certain, not from looking back from the future. That is still a useful finding for a premortem: "it has failed; why?" draws out more explanations than "what might go wrong?". But more reasons are not the same as better ones. The team still has to judge which matter, and the record should keep the ones it decided to accept as risks.
What to do
For every decision that commits money, people or another team's time, write down the decision, its owner, its basis, the risks accepted, and what would reopen it.
Keep the record next to the work it governs, not in the minutes of the meeting where it was made. Minutes record a conversation; the next review needs the decision.
When a fact in the basis changes, look at the decision again. When the date to reopen it arrives, look at it whether or not anything has changed.
In reviews, start from the record. Ask "what did we know, and has it changed?" before "was it right?".
For the big ones, run a premortem first, and put the risks you accept into the record.
This is the governance half of the line-of-sight problem I wrote about in where the missing third of a strategy goes. A dependency agreed between two owners is a small decision record of its own, saying what was asked, who agreed and by when; I wrote about that in dependencies are promises.
One line on waytrk
In waytrk, a decision on a Function plan records the decision, its reason and a fixed copy of the version that was decided on, and each maturity assessment is dated and can carry a note on what it was based on. The basis stays next to the work, where the next review will look for it.