How do you manage dependencies between projects across departments?

What actually works for dependencies between teams that report to different people?

Make every dependency between departments an explicit request: one owner asks for something specific by a date, and the owner who would have to deliver it accepts or declines, with a reason if they decline. Say whether it is needed before the waiting work starts or only before it finishes. Then compare the dates, show any conflict to both owners, and never fix a conflict by quietly moving a date. Most cross-department dependencies fail not because a promise was broken, but because none was made.

Figure 1. A dependency, handled as a promise
  1. Ask

    What is needed, described so it can be checked, and whether it is needed before the work starts or before it finishes.

  2. Accept or decline

    The providing owner agrees, or says no with a reason. Until then it is a proposal, not a plan.

  3. Check the dates

    Show conflicts and handovers with no spare time to both owners.

  4. Close the loop

    When it is delivered, the waiting owner says so.

Why departments are the weak point

Sull, Homkes and Sull's research on strategy execution found that it fails between units more than within them: managers say they can rely on their own boss and direct reports far more than on colleagues in other functions and units [1]. That is not because other departments are careless. Inside a team, commitments are made out loud. Across a boundary, they are usually assumed: one plan writes down a date from another plan, and the other team never hears about it.

Why a request works better than a dependency line

Sull and Spinosa made the case in 2007 that execution runs on promises between a customer and a provider, made in three phases: a meeting of minds, making it happen, and closing the loop, where the customer declares whether the work was delivered. Good promises, in their account, are public, active, voluntary, explicit and mission based [2]. A line on a Gantt chart drawn by the waiting team is none of those things. A request accepted by the providing owner is most of them.

Three details that matter

Be specific about what is needed. "The new case data feed, tested and live" can be checked. "Data" cannot, and both sides will read it differently.

Say when it is needed. Needed before the waiting work starts and needed before it finishes are different promises. The second leaves the provider months more room, and they cannot plan for either without knowing which.

Keep declined requests visible. A declined request is the process working: the organisation has found out early that something it assumed is not going to happen. Hiding it, or treating it as obstruction, means finding out late instead.

The reasoning behind all of this is in dependencies are promises, and the management idea it borrows is explained in what is promise-based management.

In waytrk, a dependency is proposed by one Initiative's Owner and confirmed only when both Owners confirm it, and waytrk shows timing conflicts but never moves a date.

References

Every figure above points at an entry in the evidence base, which records the source, its method, its grade and its limits.

  1. Sull, D., Homkes, R. and Sull, C. (2015) Why strategy execution unravels, and what to do about it. Harvard Business Review, March 2015. Original source (opens in a new tab)

    Grade BGrade BA named survey or study that states its method and sample. Register entry 3

  2. Sull, D. and Spinosa, C. (2007) Promise-based management, the essence of execution. Harvard Business Review, April 2007. Original source (opens in a new tab)

    Grade CGrade CAn argued source, such as a book or a method, rather than a measurement. Register entry 4

Cross-project dependencies between departments

What am I looking at?

An article from our knowledge centre on turning strategy into delivery. Every figure is traced to its source, with its limits.

Words on this page

Initiative
A piece of planned work.
Function
A team, department or service, with its own plan.
Dependency
One piece of work needs another to finish first.
Timing conflict
Work planned to start, or finish, before the work it needs has finished.
Owner
Keeps a Function's plan current and decides on suggested changes.