What should a decision record contain?

What is the minimum worth writing down about a decision, so it can be reviewed fairly later?

Four things: the decision and who made it, what it was based on, what would reopen it, and what was accepted as a risk. That fits on half a page and takes ten minutes. The part most often missing, and the most useful, is the basis: the facts, estimates and assumptions the decision rested on, and the options that were considered and why they lost. With the basis written down, a later review can ask whether the decision still stands now that something has changed, instead of arguing about whether it was right.

Figure 1. A decision record in four parts
  • The decision and its owner

    One sentence, and the name of the person who made it.

  • What it was based on

    The facts, estimates and assumptions, and the options considered and why they lost.

  • What would reopen it

    A date, or a change in one of the facts it rests on.

  • What was accepted as a risk

    What could go wrong that was seen and accepted, rather than missed.

Why the basis matters most

A decision looks different once its outcome is known. If it went well it looks obvious; if it went badly it looks careless. Either way, the people reviewing it have something the people who made it did not. A written basis is the only fair defence against that. It also makes the decision easier to revisit: if the decision rested on "the supplier delivers by June", the day the supplier slips is the day to look at it again, not the next quarterly review.

Estimates in the basis

Many decisions rest on an estimate of cost, time or benefit, and those estimates lean one way. HM Treasury's guidance on optimism bias states that project appraisers are systematically over-optimistic about cost, time and benefit, and that estimates should be adjusted using evidence from past projects [1]. Write the estimate into the basis, and say whether it was adjusted. The Treasury's own uplift percentages are UK public-sector figures, so borrow the principle more readily than the numbers.

The risks you accepted

For a big decision, look for the failure before you commit. Gary Klein's premortem asks a team to imagine the plan has already failed and explain why. The study behind it, by Mitchell, Russo and Pennington in 1989, found that people asked to explain an outcome presented as certain gave more reasons for it than people explaining the same outcome presented as uncertain: about 4.5 against 3.3 [2]. The often-quoted "30% better" is not in the paper, and it counted reasons rather than judging them. More reasons are not better ones, so the team still has to decide which to accept, and those go in the record.

The longer argument is in write down what a decision was based on, and how records feed a review is in how to run a strategy review that changes something.

In waytrk, a decision on a Function plan records the decision, its reason and a fixed copy of the version that was decided on.

References

Every figure above points at an entry in the evidence base, which records the source, its method, its grade and its limits.

  1. HM Treasury (2013) Green Book supplementary guidance, optimism bias. Original source (opens in a new tab)

    Grade AGrade AThe strongest evidence: a meta-analysis, a systematic review, a peer-reviewed empirical study, or an official body's own measurement. Register entry 13

  2. Mitchell, D. J., Russo, J. E. and Pennington, N. (1989) Back to the future, temporal perspective in the explanation of events. Journal of Behavioral Decision Making, 2(1), 25–38; applied by Klein, G. (2007) Performing a project premortem. Harvard Business Review, September 2007. Original source (opens in a new tab)

    Grade AGrade AThe strongest evidence: a meta-analysis, a systematic review, a peer-reviewed empirical study, or an official body's own measurement. Register entry 16

What should a decision log contain?

What am I looking at?

An article from our knowledge centre on turning strategy into delivery. Every figure is traced to its source, with its limits.

Words on this page

Initiative
A piece of planned work.
Function
A team, department or service, with its own plan.
Plan alternative
A copy of a plan with different dates or costs, to compare before choosing.