How should OKR status be calculated?

Is there a fair, simple rule for whether a key result is on track, and what are its limits?

The simplest fair rule compares two percentages. Progress is how far the latest measurement has moved from the baseline towards the target. Expected is how far through the period today is. If progress is level with expected or ahead of it, the key result is on track. If it is up to 10 points behind, it is Step in. If it is more than 10 points behind, it is Act now. And if there has been no measurement for 90 days, its status is Update due, whatever colour it last had. That rule is a method, not a research finding, and it has limits worth knowing.

Figure 1. A worked example Illustrative example, not data
  • The key result

    Median complaint resolution falls from 21 working days to 10 by the end of the year.

  • Expected

    Today is 60% of the way through the period, so progress should be 60%.

  • Progress

    The latest measurement is 15.4 days. That is 5.6 of the 11 days needed, or 51%.

  • Status

    9 points behind expected, so Step in. One more month like this and it will be Act now.

Why calculate at all

John Doerr's case for objectives and key results rests on objectives being significant outcomes and key results being measurable and verifiable, so that progress can be checked rather than asserted [1]. A colour chosen by hand turns into a target and stops being a measure; Marilyn Strathern's wording of the principle is that "when a measure becomes a target, it ceases to be a good measure" [2]. A rule nobody chooses avoids that.

Why a straight line

Because everyone can check it and nobody can argue with it. The straight line from baseline to target is not how most change happens: adoption can start slowly and then accelerate, savings can arrive in steps, and some measures get worse before they get better. But its errors are visible and predictable, and the owner can explain them: "we expected a slow start, and here is the evidence that it is speeding up". That is a better conversation than one about whether a colour was honestly chosen.

The alternatives each have a place. An expected curve is more accurate when you know the shape in advance, but it is drawn by the people who will be measured against it. Leading indicators help when the outcome moves too slowly to be useful. Owner judgement backed by evidence beats bare judgement, but the colour is still chosen. Whichever you use, write down why before the measurements arrive.

Two rules that keep it honest

Let owners flag a key result early, so it shows Step in, when they know trouble is coming, but never let a flag hide a worse calculated status. And treat a key result with no baseline or no target as having no status at all, rather than guessing one. The full argument is in status you set by hand drifts green, and why hand-set colours fail is in why RAG status reports go wrong.

waytrk uses this rule for Key Results: up to 10 points behind is Step in, more is Act now, and 90 days without a measurement is Update due. A Key Result on track by fewer than 5 points, or further behind at each of its last two updates, shows Watch.

References

Every figure above points at an entry in the evidence base, which records the source, its method, its grade and its limits.

  1. Doerr, J. (2018) Measure what matters. Portfolio Penguin. Original source (opens in a new tab)

    Grade CGrade CAn argued source, such as a book or a method, rather than a measurement. Register entry 20

  2. Strathern, M. (1997) Improving ratings, audit in the British university system. European Review, 5(3), 305–321, at 308. Original source (opens in a new tab)

    Grade CGrade CAn argued source, such as a book or a method, rather than a measurement. Register entry 15

How to calculate OKR status

What am I looking at?

An article from our knowledge centre on turning strategy into delivery. Every figure is traced to its source, with its limits.

Words on this page

Priority
One of the few themes your strategy focuses on.
Objective
Something the strategy sets out to change.
Key Result
A dated target that shows an Objective's progress.
OKR
Objectives and Key Results: an Objective with its Key Results.
KPI
A key performance indicator: a measure you track all the time.
Initiative
A piece of planned work.
Function
A team, department or service, with its own plan.
Owner
Keeps a Function's plan current and decides on suggested changes.