RAG reports go wrong because the colour is chosen by the people whose work is being reported on. As soon as the colour is what the steering group reads and what triggers scrutiny, it becomes a target, and people manage the colour instead of the work. Nobody needs to lie for this to happen. Amber feels like an admission, the fix is coming next month, and the person closest to the work is, reasonably, the most optimistic about it. The fix is to stop asking anyone to choose the colour.
| Set by hand | Worked out | |
|---|---|---|
| Who decides it | The person being reported on | A rule everyone shares |
| What it rests on | Judgement and mood | A baseline, a target and a date |
| When nobody updates it | It keeps its last colour | It shows no update |
| What a change means | Someone chose to change it | The measurement moved |
A measure that becomes a target
Marilyn Strathern's 1997 wording of what is usually called Goodhart's law is the one people quote: "When a measure becomes a target, it ceases to be a good measure" [1]. It is an argued point rather than a measurement, but it describes a self-reported status exactly. The colour starts as an honest summary. Once it matters, it is managed.
Optimism, built in
There is a second force pushing colours towards green. HM Treasury's guidance on optimism bias states that project appraisers are systematically over-optimistic about cost, time and benefit [2]. That guidance is about appraisals rather than status reports, so applying it here is my inference, not a finding. But it would be surprising if the same people became less optimistic once their project had started and their status was on the agenda.
What fixes it
Work status out instead of choosing it. Give each measure a baseline, a target and a date, and let a rule compare how far it has moved with how far through the period you are. Let owners raise a concern early, but never let them lower a status the rule has worked out. And when a measure has not been updated for three months, show "no update", not the last colour it had: a report that cannot say "we don't know" will say green instead.
How the rule works, and its honest alternatives, are in how OKR status should be calculated. The longer argument is in status you set by hand drifts green.
In waytrk, nobody sets a Key Result's colour by hand: status is worked out from its measurements, and one not measured in 90 days shows Update due.