Most status reports run on colours chosen by the people whose work is being reported. The colour starts as a measure: a short, honest summary of how things are going. Then it becomes the thing the steering group looks at, the thing that triggers scrutiny, the thing that goes to the board. From that point the colour is a target, and people manage the colour.
When a measure becomes a target
Marilyn Strathern's 1997 wording of what is usually called Goodhart's law is the one people quote: "When a measure becomes a target, it ceases to be a good measure" [1]. It is an argued point rather than a measurement, and the wording is hers, generalising Goodhart's observation about monetary targets. But it describes a self-reported status precisely. Nobody needs to lie for the colour to drift. Amber feels like an admission. The fix is coming next month. The person closest to the work is, reasonably, the most confident about it.
That last point has some evidence near it. HM Treasury's guidance on optimism bias states that project appraisers are systematically over-optimistic about cost, time and benefit [2]. The guidance is about appraisals, not status reports, so I am drawing an inference here, not quoting a finding. But I would be surprised if the same people became less optimistic once their project had started and their status was on the board's agenda.
Work it out instead
The alternative is to stop asking anyone to choose the colour. John Doerr's case for objectives and key results rests on the same discipline: objectives are significant outcomes, and key results are measurable and verifiable, so progress can be checked rather than asserted [3]. A key result with a baseline, a target and a date contains everything a rule needs.
The simplest rule is a straight line. Progress is how far the latest measurement has moved from the baseline towards the target. Expected is how far through the period today is. If progress is level with expected or ahead of it, the key result is on track. If it is a little behind, it shows Step in. If it is well behind, it shows Act now. That is the rule waytrk uses, and I want to be clear that it is a method, not a research finding. Doerr argues for measurement; the straight line is waytrk's choice, not his.
- Expected, a straight line from baseline to target
- Measured progress
- Step in, up to 10 points behind
- Aug: Act now, 21 points behind expected
Show the figures as a table
| Series | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Expected, a straight line from baseline to target | 0% | 9% | 18% | 27% | 36% | 45% | 55% | 64% | 73% | 82% | 91% | 100% |
| Measured progress | 0% | 10% | 19% | 27% | 31% | 37% | – | 43% | – | – | – | – |
On track
Progress is level with expected, or ahead of it.
Step in
Up to 10 points behind expected, or flagged early by the owner.
Act now
More than 10 points behind expected.
Update due
Not measured in 90 days, never measured, or no baseline or target yet.
The straight line is wrong, usefully
Plenty of change does not move in a straight line. Adoption can start slowly and then accelerate. Savings can arrive in steps, when a contract ends or a team moves. Some measures get worse before they get better. There are honest alternatives, and each has its place.
- Straight line
- Slow start, then faster
- Steps
Months from the start
Show the figures as a table
| Series | 0 | Point 2 | Point 3 | 3 | Point 5 | Point 6 | 6 | Point 8 | Point 9 | 9 | Point 11 | Point 12 | 12 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Straight line | 0% | 8% | 17% | 25% | 33% | 42% | 50% | 58% | 67% | 75% | 83% | 92% | 100% |
| Slow start, then faster | 0% | 1% | 3% | 5% | 9% | 15% | 25% | 38% | 55% | 72% | 86% | 95% | 100% |
| Steps | 0% | 0% | 0% | 0% | 30% | 30% | 30% | 30% | 65% | 65% | 65% | 65% | 100% |
An expected curve. Set the expected path for each key result as a curve or a series of steps. It is more accurate when you know the shape in advance. When you do not, it is one more place for optimism to hide, because the curve is drawn by the same people who will be measured against it.
Leading indicators. Measure something that predicts the outcome, when the outcome itself moves too slowly to be useful. Good when the link is well understood; risky when the indicator turns into a count of activity.
Judgement backed by evidence. Let the owner set the status, but require evidence for it. Better than bare judgement, but the colour is still chosen, and so still open to the drift above.
The straight line's virtue is not accuracy. It is that everyone uses the same rule and nobody chooses it. When it is wrong, it is wrong in a visible and predictable way, and the owner can explain why: "we expected a slow start; here is the evidence that it is accelerating". That is a better conversation than one about whether a colour was honestly chosen. And one asymmetry helps: let owners raise a concern early, but never let them lower a status the rule has worked out.
Where the targets come from
A calculated status is only as honest as its target and its date. If the target was optimistic, a straight line to it will show Act now from the second month, and that is information, not unfairness.
Bent Flyvbjerg's reference class forecasting takes an outside view: estimate from the actual outcomes of a class of similar past projects, rather than from the plan in front of you [4]. The Treasury asks the same of appraisers: adjust estimates using evidence from past projects. A small organisation may not have a large class of comparable projects, and the method needs one to work well. But even "what happened the last two times we tried something like this?" is a better starting point than the plan's own assumptions.
The same goes for cost. A cost figure in a status report is usually an estimate. Label it as one, say what it was based on, and keep that basis with the decision it supports.
Unknown must be allowed to exist
A key result nobody has measured for three months is not green. It is unknown. If a reporting system cannot say "we don't know", it will say green instead, because green is what an untouched status looks like.
So give Update due a place on the report, and a rule: no measurement in 90 days means Update due, whatever colour it last had. It is uncomfortable to put in front of a board, and that is the point. It is the cheapest honest signal there is.
What to do
Give every key result a baseline, a target and a date.
Work status out from a rule everyone shares. A straight line is a reasonable default; if you use a curve instead, write down why, before the measurements arrive.
Let owners raise a concern early. Never let them lower a calculated status.
Treat no measurement in 90 days as Update due, and show it.
Set targets and dates from what happened last time, and label cost figures as estimates.
This is the measurement half of the problem I described in where the missing third of a strategy goes: a portfolio can look green throughout while a third of the value quietly fails to arrive. The other half is checking that the work is aimed at the aims at all.
One line on waytrk
In waytrk nobody sets a Key Result's colour by hand. Status is worked out from the baseline, target and date against a straight line. Up to 10 points behind shows Step in, further behind shows Act now, and not measured in 90 days shows Update due. One only just on track, or further behind at each of its last two updates, shows Watch. An owner can flag one early so it shows Step in, but can never hide a worse calculated status.